Commissioning of electrical, instrumentation and control systems in the process industry - Specific phases and milestones
出版:International Electrotechnical Committee

專家解讀視頻
defines specific phases and milestones (see Figure 1) in the commissioning of electrical, instrumentation and control systems in the process industry. By way of example, it describes activities following the ""completion-of-erection"" milestone of the project and prior to the ""acceptance-of-the-plant"" phase by the owner. Such activities need to be adapted for each type of process/plant co
OVE/ONORM EN 62337:2007 - Identical
PN EN 62337:2007 - Identical
NEN EN IEC 62337:2007 - Identical
BS EN 62337:2007 - Identical
DIN EN 62337 (2007-09) - Identical
I.S. EN 62337:2007 - Identical
SS EN 62337 Ed. 1 (2008) - Identical
CEI EN 62337 Ed. 1 (2008) - Identical